City Street Updates

Active/Upcoming Road Rehabilitation Projects

*Schedules may change to accommodate weather conditions or other unforeseen factors. 

Wood St & Northington St

June 4, 2025- Beginning Thursday, June 12, road construction will begin on Wood Street and Northington Street to improve drainage, add curb and gutter, and provide new pavement. The project is expected to be completed by September 3 and will be carried out in phases. Each affected resident should have received a door hanger notice with specific details about the construction timeline for their area. Please see attachment below for Wood St & Northington St Road Closure for maps. 

DETOUR & PARKING NOTICE:
• Street parking will not be allowed on the affected streets during construction.
• Residents will need to park on adjacent side streets during construction phases.
• Detour signs will be posted to help guide residents around the work zones.
• Emergency vehicle access will be maintained at all times.

Phase Schedule (maps attached):
Phase 1: Wood St. (Dougherty Creek to 963)- June 12 – July 12
Phase 2: Wood St. (Brier St. to Kerr St.)- June 12 – July 12
Phase 3: Wood St. (SH-29 to Brier St.)- July 14 – August 15
Phase 5: Northington St. (Rhomberg to Wallace Riddell Parking Lot)- July 14 – August 15
Phase 6: Northington St. (Hill St. to Wallace Riddell Parking Lot)- August 16 – September 3
Phase 7: Wood St. (Kerr St. to Dougherty Creek)- July 14 – August 15 (Open to traffic but under construction)
For questions, please email the contractor at zach@gageandcadeconstruction.com or contact the City of Burnet at 512-756-2402

Houston Clinton  Drive Closure: March 27 - May

UPDATE 5-16-2025: The road construction on Houston Clinton is ahead of schedule! The westbound lane will remain closed through this week and part of next, reopening each afternoon. Curbs are being installed along the north side, and the first layer of asphalt is set for next Wednesday. Once paving is complete, work will shift to the eastbound lane. Unlike previous sections, this phase will receive its final asphalt layer at the end of the project to improve surface quality

Original Post March 14, 2025- The first portion of Houston Clinton at SH-281 will be closed for demolition. This closure will require traffic to be rerouted through Cary Johnson Parkway. Please see attachment below for Houston Clinton Road Closure for more information.

 

This map displays all the streets that have been maintained over the past three years (since 2022), along with their current roadway conditions. It also provides a glimpse of the tentative schedule for upcoming road repairs. For more detailed information on upcoming road repairs please see information below the map. If there are active projects underway, you can find more detailed information about those repairs in the section located beneath the map.